Thua Thien – Hue proposed to revoke the right to use and revoke the license of the hydroelectric power plant Thuong Nhat | News



On the afternoon of November 21, the People’s Committee of Thua Thien-Hue Province said that the Chairman of the People’s Committee of Thua Thien-Hue Province signed an official letter to the Ministry of Industry and Trade and the Ministry of Natural Resources and Environment requesting the revocation of two important permits for Thuong Nhat ). Nhat, H. Nam Dong, Thua Thien – Hue).

In particular, the People’s Committee of Thua Thien-Hue Province requested the Ministry of Industry and Trade to instruct the Electricity Regulatory Authority to consider revoking the electricity license in the area of ​​electricity production activities of the Central Viet Hydropower Investment Joint Stock Company. South (investor in Thuong Nhat hydroelectric power plant).

In addition, the People’s Committee of Thua Thien-Hue Province requested the Ministry of Natural Resources and Environment to instruct the Department of Water Resources to consider revoking the right to use the permit or revoking the permit for exploitation and use of surface water granted to the Thuong Nhat hydropower plant. .

In addition to the request for revocation of the license, the People’s Committee of the Province of Thua Thien – Hue also asked the Department of Safety and Environmental Engineering – Ministry of Industry and Trade to consider and sanction administrative violations against the joint stock company Hidropover Investment. Central Vietnam.

According to the People’s Committee of Thua Thien-Hue Province, the Provincial People’s Committee allowed the Thuong Nhat hydroelectric power plant to accumulate water from the Phase 1 reservoir on June 6, 2020 to a normal water level rise of 116 m, for implementation within 90 days. permeability test, trial operation, calibration experiment, complete downstream elements of the hydroelectric power plant …

At the end of this time, after the inspection, the Provincial People’s Committee issued an official letter not to allow the official operation of the Thuong Nhat hydroelectric power plant, asking the investor to exceed the conditions for filling with water. However, so far the project has not been completed to overcome the existing problems, it is not yet qualified for water storage.

Thua Thien - Hue proposed to revoke the right to use and revoke the license of the hydroelectric power plant Thuong Nhat - photo 1

The inspection team of the Ministry of Industry and Trade is inspecting the Thuong Nhat hydroelectric power plant

In the 2020 flood season, the Central Vietnamese Joint Stock Company for Hydropower does not strictly follow the disaster response direction of the Thua Thien-Hue Provincial People’s Committee, does not adhere to the reservoir operation process and does not follow the command to manage the Provincial People’s Committee’s reservoir.

With its powers, the Thua Thien-Hue Provincial People’s Committee is also awaiting an explanation from investors, consolidating the file to sanction VND 500 million for violations committed by the provincial Department of Natural Resources and Environment against investors. Thuong Nhat Hydropower Company.